a website collaboration between Science Service and the Smithsonian Institution

1943 - this power plant must work for 20 hours to store up enough chilled water for each stratosphere test in the chamber

STRATOSPHERE "GENERATORS"

CD 1963036 E&MP 21.021

Electric Generators

May 1943

This massive bank of machinery, including compressors, motors and condensers is required to generate stratosphere weather in a single York strato-chamber.

Equipment supplies the necessary chilled water to chamber to drop temperature to 70 degrees below zero in a few minutes.

This power plant must work for 20 hours to store up enough chilled water for each stratosphere test in the chamber. 

Original Caption by Science Service
©York Ice Machinery Corporation



National Museum of American History